§ 8. Construction inspection.  


Latest version.
  • 8.1

    The applicant shall notify the building code services division in advance before the commencement of construction.

    8.2

    On-site inspections shall be conducted by building code services division or the engineering department who shall inspect the work and notify the permittee wherein the work fails to comply with the erosion and sediment control plan as approved.

    8.2.1 Plans for grading, stripping, excavating, and filling work bearing the stamp of approval of the building official or city engineer shall be maintained at the site during the progress of the work. To obtain required inspections, the permittee shall notify the city as follows:

    8.2.1.1 Two (2) days before the start of construction.

    8.2.1.2 Upon completion of site clearing.

    8.2.1.3 Upon completion of rough grading.

    8.2.1.4 Upon completion of final grading.

    8.2.1.5 Upon completion of final landscaping.

    8.2.2 The city engineer or public works director shall act as designated agent and inspector for all construction done by their employees. All contract work done for the city shall be the responsibility of the contractor and shall comply with the provisions herein.

    8.3

    The city maintains the right to enter the property of the applicant as deemed necessary to make inspection and to ensure compliance.

(Ord. No. 2419, § 1, 1-19-05)